Context
A leaf of #21346, the planning examples under #21140. The visitor's question: can the table beside the bars carry our columns: an outline number, an owner, dates, days, progress?
No contributor labels: the capability is read from the source (the check on #21346) and has not been driven in a browser. A maintainer builds it, and the drive is the first step.
The Problem
Both Gantt examples show one column, the task tree. A project manager reads the table as much as the bars, and the engine's task side takes column descriptors.
The Architectural Reality
taskColumns_ (src/gantt/Container.mjs:71): descriptors for the locked task columns. The default is one tree column, {type: 'tree', dataField: 'title', locked: 'start'}.
- Tree filtering exists and is untested in the Gantt, and a cell edit does not cascade (the source check linked above). The columns of this example are read-only.
- Template:
examples/gantt/basic (not edited). Specs for the family: test/playwright/e2e/gantt/.
- Shared files stay out of this pull request (
#21539: every examples pull request that edits them makes the others stale): the catalog's data, its two specs and test/playwright/externalBrainSelection.mjs belong to #21613, which takes the record below as written.
- Design authority: n/a — a new example; it calls no existing behaviour wrong.
The Fix
- Drive it first on a scratch copy of the base example: seven columns, two of them with a renderer, a collapsed phase, and a horizontal scroll of the chart. A defect becomes an engine ticket, linked here as a blocker.
- A new folder
examples/gantt/taskColumns: a festival's production plan. About 30 tasks in five phases. The columns: outline number, task (the tree), owner with initials in a badge, start, end, days, and percent done as a small bar. The data ships with the example, in stores of models.
- The record, for #21613: id
gantt-task-columns, name "Your columns beside the plan", feature "Seven task columns: outline number, tree, owner, dates, days and a progress bar", lookFor "Collapse a phase: its rows fold in the table and in the chart together. Scroll the chart: the columns stay." Cover: the table with its owner badges and progress bars, the chart beside it.
Acceptance Criteria
Out of Scope
Engine changes. Editable cells. Tree filtering. Reordering or resizing the columns.
Avoided Traps
- Seven columns of plain text. Two of them show what a renderer can do.
- Columns so wide that the chart disappears.
Related
Parent #21346 · #21140 (the Gantt row of its content table) · #21613 (publication) · #21619 (the scheduler's resource columns).
unowned-rationale: open to a maintainer now. It ships with Engine 14 if it has merged by Sun 22 Nov 12:00 CET, so that #21613 can publish it before the lock; otherwise the week after.
Live latest-open + closed sweep: latest 20 open read (62 open before this batch, red band: a leaf of the owning epic #21346), open and closed search ("scheduler OR gantt OR board example", titles read; #21355, #21356 and #21357 are the three examples this epic has delivered) at 2026-11-20T18:41Z: no equivalent and no prior exclusion. A2A in-flight sweep: the latest 12 messages, all read-states, back to 18:23Z: no claim on a planning example. MC sweep ("scheduler, Gantt and task board show two examples each; which new planning examples does the release need"): 6 results, turns of 7 to 20 Nov, no decision that excludes this example. Own-assignment sweep: 8 open; #21346 is the parent.
Decision Record impact: none.
Origin Session ID: d33dee4c-5fa8-4403-8864-4f146d8a50c9
Retrieval Hint: "Gantt example task columns, taskColumns descriptors, outline number, owner badge, progress bar beside the task tree"
📜 Clio · @neo-fable-clio · Claude Fable 5.2 · Claude Code
Context
A leaf of #21346, the planning examples under #21140. The visitor's question: can the table beside the bars carry our columns: an outline number, an owner, dates, days, progress?
No contributor labels: the capability is read from the source (the check on
#21346) and has not been driven in a browser. A maintainer builds it, and the drive is the first step.The Problem
Both Gantt examples show one column, the task tree. A project manager reads the table as much as the bars, and the engine's task side takes column descriptors.
The Architectural Reality
taskColumns_(src/gantt/Container.mjs:71): descriptors for the locked task columns. The default is one tree column,{type: 'tree', dataField: 'title', locked: 'start'}.examples/gantt/basic(not edited). Specs for the family:test/playwright/e2e/gantt/.#21539: every examples pull request that edits them makes the others stale): the catalog's data, its two specs andtest/playwright/externalBrainSelection.mjsbelong to #21613, which takes the record below as written.The Fix
examples/gantt/taskColumns: a festival's production plan. About 30 tasks in five phases. The columns: outline number, task (the tree), owner with initials in a badge, start, end, days, and percent done as a small bar. The data ships with the example, in stores of models.gantt-task-columns, name "Your columns beside the plan",feature"Seven task columns: outline number, tree, owner, dates, days and a progress bar",lookFor"Collapse a phase: its rows fold in the table and in the chart together. Scroll the chart: the columns stay." Cover: the table with its owner badges and progress bars, the chart beside it.Acceptance Criteria
test/playwright/e2e/gantt/asserts the column count and that table rows and chart rows match after a collapse.neo-config.jsonlists.gantt/basic's, read cold by one reader of the builder's seat. Numbers are right-aligned, dates share one format, and the badge and the progress bar are designed for the dark and the light theme.Out of Scope
Engine changes. Editable cells. Tree filtering. Reordering or resizing the columns.
Avoided Traps
Related
Parent #21346 · #21140 (the Gantt row of its content table) · #21613 (publication) · #21619 (the scheduler's resource columns).
unowned-rationale: open to a maintainer now. It ships with Engine 14 if it has merged by Sun 22 Nov 12:00 CET, so that #21613 can publish it before the lock; otherwise the week after.
Live latest-open + closed sweep: latest 20 open read (62 open before this batch, red band: a leaf of the owning epic #21346), open and closed search ("scheduler OR gantt OR board example", titles read;
#21355,#21356and#21357are the three examples this epic has delivered) at 2026-11-20T18:41Z: no equivalent and no prior exclusion. A2A in-flight sweep: the latest 12 messages, all read-states, back to 18:23Z: no claim on a planning example. MC sweep ("scheduler, Gantt and task board show two examples each; which new planning examples does the release need"): 6 results, turns of 7 to 20 Nov, no decision that excludes this example. Own-assignment sweep: 8 open; #21346 is the parent.Decision Record impact: none.
Origin Session ID: d33dee4c-5fa8-4403-8864-4f146d8a50c9
Retrieval Hint: "Gantt example task columns, taskColumns descriptors, outline number, owner badge, progress bar beside the task tree"