A leaf of #21346, the planning examples under #21140. The visitor's question: what happens to my plan when one task slips?
No contributor labels: the capability is on dev and five examples set its configs, but none has been driven for this question. A maintainer builds it, and the drive is the first step.
The Problem
Every buyer of a Gantt chart asks it first, and no card answers it. The cascade runs in five examples as a side effect of another point (an editor, a link drag, working days). None shows how far a slip reaches, and a visitor has to find a bar and drag it before anything moves.
The Architectural Reality
cascadeDependencies_ (src/gantt/Container.mjs:50, default true) recomputes dependent tasks after an edit. animateCascade_ (:44, default false, from #21639) moves the changed bars and their links from their previous dates to the new ones (:1089-1097). Read on dev3ed1cf5b6c.
Template: examples/gantt/basic (not edited). Specs for the family: test/playwright/e2e/gantt/.
Data sets already taken by the family: a garden, a building programme, a kitchen, a product launch, a website relaunch.
Publication: #21613 is closed, and this is a wave of one. As the exception to rule 4 of #21346's body, this pull request carries its own record, recipe and e2e selection entry. One open pull request touches examples.json tonight (#21515, an outside contributor's, already conflicting).
Design authority: n/a — a new example; it calls no existing behaviour wrong.
The Fix
Drive it first on a scratch copy of the base example: delay a task that has a chain of successors, by a button and by a drag, with cascadeDependencies on and off and animateCascade on and off. What the engine reports about a cascade (which tasks moved, and by how much) decides how the readout is built. A defect becomes an engine ticket, linked here as a blocker.
A new folder examples/gantt/cascade: an office move. Twelve linked tasks on fixed dates: one chain from "Sign the lease" to "First day in the new office", and two tasks beside the chain that a slip does not touch. Above the plan one line names the move day; after a slip it names the old and the new day and how many tasks moved. Two controls: "Delay the cabling by a week" and "Reset". The data ships with the example, in stores of models.
The record: id gantt-cascade, name "A late task moves the plan", feature "One task slips, and every task that depends on it follows to its new date", lookFor "Press 'Delay the cabling by a week', or drag its bar: the tasks behind it glide to their new dates, the two beside the chain stay, and the line above the plan says how far the move day slipped." Cover: the plan after the delay, with the line showing both days.
Acceptance Criteria
On the first frame the chain and the move day are readable without a click.
One press delays the task; its successors move in motion, the two tasks beside the chain keep their dates, and the line names the old and the new move day and the count of moved tasks.
A drag of the same bar does the same, and Reset restores the first frame.
A spec under test/playwright/e2e/gantt/ asserts the move day and one successor's start before and after the delay, on fixed dates.
No console error. 1440 × 900 and 390 × 844. Every theme the base example's neo-config.json lists.
Look: the first frame and the frame after the delay, at both sizes in the dark theme, are on the pull request, read cold by one reader of the builder's seat with one question: what happened to the plan? A control's mark is its iconCls, never a typed arrow.
The record, the recipe (theme: dark) and the e2e selection entry are in this pull request, and the cover goes to neomjs/pages with it.
Out of Scope
Engine changes. A task editor (gantt-task-editor shows the cascade after a form save). Critical path, slack and baselines. The other four examples #21346 is short of.
Avoided Traps
A delayed task without successors, or a plan in which every task sits on the chain. The first shows nothing; the second hides that a cascade is selective.
Dates relative to today. The chain has to sit where the first frame needs it.
A second task-editor example. Here the slip comes from one button and one drag.
Related
Parent #21346 · #21140 (the Gantt row of its content table) · #21639 (the transition) · #21624 (the task editor example) · #21613 (the first publication wave).
Ownership: handoff offered to @neo-gpt-euclid by direct message on 22 Nov (he published the nineteen planning records in #21805); unclaimed until he or another maintainer claims it. It ships with Engine 14 if it has merged by Sun 22 Nov 12:00 CET and its cover is on pages before the lock at 18:00 CET; otherwise it is the first example of the week after.
Live latest-open + closed sweep: checked the latest 20 open plus open and closed searches ("gantt cascade example", "late task moves the plan", "cascade successors follow") at 2026-11-21T23:40Z; read Acceptance Criteria, Out of Scope and Avoided Traps of the closed #21639, whose Related line already names "the cascade example" under #21346. No equivalent and no prior exclusion. Backlog band: 44 open, orange; this is a leaf of the owning epic #21346, reopened tonight. A2A in-flight sweep: the latest 12 lane claims in all read states, newest 23:38Z, none on a planning example. MC sweep: "what happens to the plan when one task slips, Gantt cascade as its own example", 5 results, no decision that excludes it. Own-assignment sweep: 6 open; #21346 is the parent. Structure-map: N/A.
Decision Record impact: none.
Origin Session ID: 55e3f57a-b16c-4b0c-ba48-8ef61262578a (the session's earlier turns were saved under 25ab3983-418c-43b6-89dc-f344340886dc; the bridge answered 502 once at 23:39Z and the id rotated)
Retrieval Hint: "Gantt cascade example, a late task moves the plan, animateCascade, cascadeDependencies, office move"
📜 Clio · @neo-fable-clio · Claude Fable 5.2 · Claude Code · session 55e3f57a-b16c-4b0c-ba48-8ef61262578a
tobiu referenced in commit 74d9991 - "feat(examples): show a late task moving an office-move Gantt plan (#21844) (#21852) on Nov 22, 2026, 6:36 AM
Context
A leaf of #21346, the planning examples under #21140. The visitor's question: what happens to my plan when one task slips?
No contributor labels: the capability is on
devand five examples set its configs, but none has been driven for this question. A maintainer builds it, and the drive is the first step.The Problem
Every buyer of a Gantt chart asks it first, and no card answers it. The cascade runs in five examples as a side effect of another point (an editor, a link drag, working days). None shows how far a slip reaches, and a visitor has to find a bar and drag it before anything moves.
The Architectural Reality
cascadeDependencies_(src/gantt/Container.mjs:50, defaulttrue) recomputes dependent tasks after an edit.animateCascade_(:44, defaultfalse, from#21639) moves the changed bars and their links from their previous dates to the new ones (:1089-1097). Read ondev3ed1cf5b6c.examples/gantt/basic(not edited). Specs for the family:test/playwright/e2e/gantt/.#21613is closed, and this is a wave of one. As the exception to rule 4 of #21346's body, this pull request carries its own record, recipe and e2e selection entry. One open pull request touchesexamples.jsontonight (#21515, an outside contributor's, already conflicting).The Fix
cascadeDependencieson and off andanimateCascadeon and off. What the engine reports about a cascade (which tasks moved, and by how much) decides how the readout is built. A defect becomes an engine ticket, linked here as a blocker.examples/gantt/cascade: an office move. Twelve linked tasks on fixed dates: one chain from "Sign the lease" to "First day in the new office", and two tasks beside the chain that a slip does not touch. Above the plan one line names the move day; after a slip it names the old and the new day and how many tasks moved. Two controls: "Delay the cabling by a week" and "Reset". The data ships with the example, in stores of models.gantt-cascade, name "A late task moves the plan",feature"One task slips, and every task that depends on it follows to its new date",lookFor"Press 'Delay the cabling by a week', or drag its bar: the tasks behind it glide to their new dates, the two beside the chain stay, and the line above the plan says how far the move day slipped." Cover: the plan after the delay, with the line showing both days.Acceptance Criteria
test/playwright/e2e/gantt/asserts the move day and one successor's start before and after the delay, on fixed dates.neo-config.jsonlists.iconCls, never a typed arrow.theme: dark) and the e2e selection entry are in this pull request, and the cover goes toneomjs/pageswith it.Out of Scope
Engine changes. A task editor (
gantt-task-editorshows the cascade after a form save). Critical path, slack and baselines. The other four examples #21346 is short of.Avoided Traps
Related
Parent #21346 · #21140 (the Gantt row of its content table) ·
#21639(the transition) ·#21624(the task editor example) ·#21613(the first publication wave).Ownership: handoff offered to @neo-gpt-euclid by direct message on 22 Nov (he published the nineteen planning records in
#21805); unclaimed until he or another maintainer claims it. It ships with Engine 14 if it has merged by Sun 22 Nov 12:00 CET and its cover is onpagesbefore the lock at 18:00 CET; otherwise it is the first example of the week after.Live latest-open + closed sweep: checked the latest 20 open plus open and closed searches ("gantt cascade example", "late task moves the plan", "cascade successors follow") at 2026-11-21T23:40Z; read Acceptance Criteria, Out of Scope and Avoided Traps of the closed
#21639, whose Related line already names "the cascade example" under #21346. No equivalent and no prior exclusion. Backlog band: 44 open, orange; this is a leaf of the owning epic #21346, reopened tonight. A2A in-flight sweep: the latest 12 lane claims in all read states, newest 23:38Z, none on a planning example. MC sweep: "what happens to the plan when one task slips, Gantt cascade as its own example", 5 results, no decision that excludes it. Own-assignment sweep: 6 open; #21346 is the parent. Structure-map: N/A.Decision Record impact: none.
Origin Session ID: 55e3f57a-b16c-4b0c-ba48-8ef61262578a (the session's earlier turns were saved under 25ab3983-418c-43b6-89dc-f344340886dc; the bridge answered 502 once at 23:39Z and the id rotated)
Retrieval Hint: "Gantt cascade example, a late task moves the plan, animateCascade, cascadeDependencies, office move"
📜 Clio · @neo-fable-clio · Claude Fable 5.2 · Claude Code · session 55e3f57a-b16c-4b0c-ba48-8ef61262578a