Please comment to claim before starting; check current assignees and linked PRs.
Context
Engine 14 (cut on Nov 23, ROADMAP.md) adds a Gantt chart: Neo.gantt.Container shows a task tree with bars, dependency arrows and a cascade that moves dependent tasks after an edit. Epic #20874 asks for "a runnable example and a guide per family". The example exists, examples/gantt/basic. The learning section has no page for the Gantt chart (git ls-tree -r origin/dev learn/, no file named for it, at b6e691cf).
The Problem
A developer, or a coding agent asked for "a project plan", finds the class and one example. Nothing says how tasks form a tree, how a dependency is a record, which four link types exist, or what the cascade and working time change. Today that is learned from the 135 lines of examples/gantt/basic/Viewport.mjs and from one-line JSDoc per config.
The Architectural Reality
All paths are on dev at b6e691cf.
src/gantt/Container.mjs: Neo.gantt.Container, ntype: 'gantt', extends Neo.scheduler.Container and inherits its time axis, bar and editing configs.
- Tasks:
store is a Neo.gantt.TaskStore (src/gantt/TaskStore.mjs, a Neo.data.TreeStore) of Neo.gantt.TaskModel records (src/gantt/TaskModel.mjs, a Neo.data.TreeModel). Fields: id, title, description, startDate, endDate, allDay, resourceId, plus collapsed, duration, durationUnit, milestone, percentDone, and the tree fields such as parentId and isLeaf.
- Dependencies:
dependencyStore is a Neo.gantt.DependencyStore of Neo.gantt.DependencyModel records with id, fromId, toId, type, lag, lagUnit. src/gantt/Cascade.mjs handles the types FS, SS, FF and SF.
- Configs of its own:
cascadeDependencies (default true, recompute dependent tasks after an edit), dependencyCreation (default false; a Boolean or a function that enables or filters link gestures), useWorkingTime (default false, durations use the axis calendar), taskColumns (the locked tree columns), schedule (an optional service the application lends the chart).
- The example passes both stores inline:
store: {module: TaskStore, data: tasks} and dependencyStore: {module: DependencyStore, data: dependencies}, and it keeps its plan across a reload.
- The pattern for a guide page:
learn/guides/datahandling/Grids.md (frontmatter with seoTitle and seoDescription, then one # title) and its line in learn/tree.json.
Design authority: n/a — calls no existing behavior wrong.
The Fix
One page, learn/guides/datahandling/Gantt.md, and one line for it in learn/tree.json after the grid pages of guides/datahandling. Seven sections, in this order:
- What a Gantt chart is here: a task tree and a dependency list, both as records.
- A minimal chart: three tasks under one parent and one dependency.
- The task record: dates, duration, milestone, progress, and how
parentId builds the tree.
- The dependency record:
fromId, toId, the four types, lag and lagUnit, with one picture or table that shows what each type constrains.
- The cascade: what moves when a task moves, and what
cascadeDependencies: false changes.
- Working time:
useWorkingTime with the axis's non-working days.
- Creating links by gesture with
dependencyCreation, and where to go next.
Between 150 and 300 lines. Every code block is taken from examples/gantt/basic or checked against it, so that it runs.
Acceptance Criteria
Out of Scope
The schedule service beyond one sentence that it exists; a critical path; server-backed loading; the scheduler's own guide; any change under src/.
Avoided Traps
- Describing the cascade from the code alone. Section 5 states what was observed in the running example.
- A reference dump of every config.
- Hand-mapped arrays. Tasks and dependencies are records of two stores.
Related
#20874 (parent; the family landed with #20878), #20498 (the standard for examples and the learning section). The scheduler's guide is a sibling issue filed the same hour; this page may link it once it exists.
unowned-rationale: Ready for a contributor; maintainers provide planning and review. The place under guides/datahandling is a default that the steward of #20874 may change.
Live latest-open + closed sweep: the latest 20 open and an open and closed search (scheduler guide, Gantt guide, timeline example) at 2026-11-15T16:59Z; 54 open, the red band, and no ticket or epic leaf owns this page: #20878 closed without one. A2A in-flight claim sweep: the newest rows to 16:59Z, no claim on this scope. MC sweep: "no guide for the scheduler or the Gantt chart", 5 results, no prior decision. Own-assignment sweep: none overlapping.
Origin Session ID: 3b1cda7a-2168-43fb-a65e-dc792af81989
Retrieval Hint: "Gantt guide learn datahandling TaskStore DependencyStore cascade FS SS FF SF curated issue"
🪢 Mnemosyne (Claude Fable 5.2, Claude Code)
Please comment to claim before starting; check current assignees and linked PRs.
Context
Engine 14 (cut on Nov 23,
ROADMAP.md) adds a Gantt chart:Neo.gantt.Containershows a task tree with bars, dependency arrows and a cascade that moves dependent tasks after an edit. Epic #20874 asks for "a runnable example and a guide per family". The example exists,examples/gantt/basic. The learning section has no page for the Gantt chart (git ls-tree -r origin/dev learn/, no file named for it, atb6e691cf).The Problem
A developer, or a coding agent asked for "a project plan", finds the class and one example. Nothing says how tasks form a tree, how a dependency is a record, which four link types exist, or what the cascade and working time change. Today that is learned from the 135 lines of
examples/gantt/basic/Viewport.mjsand from one-line JSDoc per config.The Architectural Reality
All paths are on
devatb6e691cf.src/gantt/Container.mjs:Neo.gantt.Container,ntype: 'gantt', extendsNeo.scheduler.Containerand inherits its time axis, bar and editing configs.storeis aNeo.gantt.TaskStore(src/gantt/TaskStore.mjs, aNeo.data.TreeStore) ofNeo.gantt.TaskModelrecords (src/gantt/TaskModel.mjs, aNeo.data.TreeModel). Fields:id,title,description,startDate,endDate,allDay,resourceId, pluscollapsed,duration,durationUnit,milestone,percentDone, and the tree fields such asparentIdandisLeaf.dependencyStoreis aNeo.gantt.DependencyStoreofNeo.gantt.DependencyModelrecords withid,fromId,toId,type,lag,lagUnit.src/gantt/Cascade.mjshandles the typesFS,SS,FFandSF.cascadeDependencies(defaulttrue, recompute dependent tasks after an edit),dependencyCreation(defaultfalse; a Boolean or a function that enables or filters link gestures),useWorkingTime(defaultfalse, durations use the axis calendar),taskColumns(the locked tree columns),schedule(an optional service the application lends the chart).store: {module: TaskStore, data: tasks}anddependencyStore: {module: DependencyStore, data: dependencies}, and it keeps its plan across a reload.learn/guides/datahandling/Grids.md(frontmatter withseoTitleandseoDescription, then one#title) and its line inlearn/tree.json.Design authority: n/a — calls no existing behavior wrong.The Fix
One page,
learn/guides/datahandling/Gantt.md, and one line for it inlearn/tree.jsonafter the grid pages ofguides/datahandling. Seven sections, in this order:parentIdbuilds the tree.fromId,toId, the four types,lagandlagUnit, with one picture or table that shows what each type constrains.cascadeDependencies: falsechanges.useWorkingTimewith the axis's non-working days.dependencyCreation, and where to go next.Between 150 and 300 lines. Every code block is taken from
examples/gantt/basicor checked against it, so that it runs.Acceptance Criteria
learn/guides/datahandling/Gantt.mdexists withseoTitleandseoDescriptionfrontmatter and the seven sections above.src/gantt,src/schedulerorsrc/timelineon the pull request's base. The pull request lists them with file and line.learn/tree.jsonregisters the page;npm run check-relative-linksand CI'sunitjob pass.Out of Scope
The
scheduleservice beyond one sentence that it exists; a critical path; server-backed loading; the scheduler's own guide; any change undersrc/.Avoided Traps
Related
#20874 (parent; the family landed with #20878), #20498 (the standard for examples and the learning section). The scheduler's guide is a sibling issue filed the same hour; this page may link it once it exists.
unowned-rationale: Ready for a contributor; maintainers provide planning and review. The place under
guides/datahandlingis a default that the steward of #20874 may change.Live latest-open + closed sweep: the latest 20 open and an open and closed search (scheduler guide, Gantt guide, timeline example) at 2026-11-15T16:59Z; 54 open, the red band, and no ticket or epic leaf owns this page: #20878 closed without one. A2A in-flight claim sweep: the newest rows to 16:59Z, no claim on this scope. MC sweep: "no guide for the scheduler or the Gantt chart", 5 results, no prior decision. Own-assignment sweep: none overlapping.
Origin Session ID: 3b1cda7a-2168-43fb-a65e-dc792af81989
Retrieval Hint: "Gantt guide learn datahandling TaskStore DependencyStore cascade FS SS FF SF curated issue"
🪢 Mnemosyne (Claude Fable 5.2, Claude Code)